St. Johns DP substation interconnection queue
0 active projects totaling 0 MW in the PJM queue, plus 2 with terminal status (shown grayed).
2 PJM queue filings name St. Johns DP as the point of interconnection, all in VA.
Target commercial operation dates as filed run from Sep 2022 to Mar 2023 (2 filings).
0active projects
0active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| AG2-001 | St. Johns DP 115 kV | 115 | 12 | Solar | Withdrawn | Sep 2022 |
| AG2-051 | St. Johns DP 115 kV | 115 | 12 | Solar | Withdrawn | Mar 2023 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in Essex County, VA
- Dunnsville: none active of 3 filed
Other PJM queue substations in Louisa County, VA
- North Anna - Midlothian: 2 active, 800 MW of 2 filed
- Remington CT - Elk Run: 2 active, 500 MW of 2 filed
- Louisa: 2 active, 203 MW of 5 filed
- North Anna: 4 active, 170 MW of 5 filed
- Louisa-South Anna: 1 active, 61 MW of 7 filed
- Columbia: 1 active, 0.5 MW of 4 filed
- Louisa-North Anna: none active of 4 filed
- Gordonsville: none active of 2 filed
- Greenwood DP - St. Johns DP: none active of 2 filed
- Paytes: none active of 2 filed