North Longview substation interconnection queue
2 active projects totaling 1,245 MW in the PJM queue, plus 2 with terminal status (shown grayed).
Target commercial operation dates as filed run from Jun 2018 to Jun 2031 (4 filings). 1 active filing targets a date after November 27, 2026.
2active projects
1,245active MW
4total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| AE1-105 | Maidsville CCGT | 500 | 1,235 | Gas | Engineering and Procurement | Jun 2031 |
| AI2-443 | North Longview 500 kV | 500 | 295 | Hybrid | Withdrawn | Jul 2027 |
| AF1-297 | North Longview 500 kV | 500 | 31.7 | Solar | Withdrawn | Apr 2022 |
| AC1-140 | Longview Power | 500 | 10 | Coal | In Service | Jun 2018 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in Preston County, WV
- Mount Storm - Pruntytown: 2 active, 231 MW of 2 filed
- Afton: none active of 2 filed
- Albright: none active of 2 filed
- Garrett - Albright: none active of 2 filed
- Horse Shoe Run: none active of 2 filed
Other PJM queue substations in Greene County, PA
Other PJM queue substations in Monongalia County, WV
- Fort Martin: 2 active, 1,613.5 MW of 3 filed
- Ft. Martin - Kammer: 1 active, 100 MW of 2 filed
Site Scanner