Substation Scout

North Longview substation interconnection queue

2 active projects totaling 1,245 MW in the PJM queue, plus 2 with terminal status (shown grayed).

Target commercial operation dates as filed run from Jun 2018 to Jun 2031 (4 filings). 1 active filing targets a date after November 27, 2026.

2active projects
1,245active MW
4total filed
Queue IDProjectkVMWResourceStatusTarget COD
AE1-105 Maidsville CCGT 500 1,235 Gas Engineering and Procurement Jun 2031
AI2-443 North Longview 500 kV 500 295 Hybrid Withdrawn Jul 2027
AF1-297 North Longview 500 kV 500 31.7 Solar Withdrawn Apr 2022
AC1-140 Longview Power 500 10 Coal In Service Jun 2018

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Other PJM queue substations in Preston County, WV

All 24 PJM queue filings in Preston County, WV.

Other PJM queue substations in Greene County, PA

All 29 PJM queue filings in Greene County, PA.

Other PJM queue substations in Monongalia County, WV

All 12 PJM queue filings in Monongalia County, WV.