Preston, WV interconnection queue

2 active projects totalling 1,466 MW in the PJM queue, plus 22 with terminal status (shown greyed).

2active projects
1,466active MW
24total filed
Queue IDProjectkVMWResourceStatus
AE1-105 Maidsville CCGT 500 1,235 Gas Engineering and Procurement
C01-1725 Mount Storm - Pruntytown 500 kV 500 231 Wind Active
W2-043 Albright-Snowy Creek 138kV 138 101 Not reported Withdrawn
D08_W18 Terra Alta 138 kV 138 88 Gas Withdrawn
AI1-211 Brandonville - Necessity 138 kV 138 68 Hybrid Withdrawn
AH2-255 Not reported n/r 65 Hybrid Withdrawn
AE1-106 Brandonville Solar 138 59 Solar Withdrawn
AH2-260 Garrett - Albright 138 kV 138 42 Solar Withdrawn
AH1-593 Hazelton 138 n/r 39 Solar Withdrawn
AI2-365 Lake Lynn-Hazelton 138 kV II 138 32.1 Solar Withdrawn
AH1-594 Hazelton 138kV 138 32 Battery Withdrawn
AG1-233 Glade Run Solar Energy Center 138 30 Solar Withdrawn
AG2-472 Jennings-Hazelton 138kV 138 30 Solar Withdrawn
AH1-340 Preston County Solar Project 138 29.3 Solar Withdrawn
AH2-261 Garrett - Albright 138 kV 138 28 Battery Withdrawn
G36_W58 Horse Shoe Run 69 kV 69 20 Gas Withdrawn
P52 Albright 138kV 138 16 Wind Withdrawn
Q55 Snowy Creek n/r 12.5 Wind Withdrawn
AI2-182 Jennings-Hazelton 138kV II 138 12 Solar Withdrawn
D03_W15 Horse Shoe Run 69 kV 69 12 Gas Withdrawn
N33 North Briery WF 138 12 Wind Withdrawn
AD1-068 Albright-Garrett 138 kV 138 11.8 Wind Withdrawn
W4-007 Afton 138kV 138 2.6 Wind Withdrawn
AH1-286 Bradford North 34.5kV 34.5 0 Solar Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.