Wild Grains Solar

PJM queue ID AF2-014

Wild Grains Solar (AF2-014) is listed in the PJM interconnection queue as a 90 MW solar project in Van Wert County, OH. The filing names Maddox Creek as its point of interconnection. PJM lists its status as “Under Construction”, with a target commercial operation date of December 31, 2027.

Queue IDAF2-014
Project nameWild Grains Solar
Status (as published)Under Construction
SubstationMaddox Creek
Point of interconnectionMaddox Creek 345 kV
CountyVan Wert
StateOH
Voltage345 kV
Capacity90 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Target commercial operation2027-12-31
Source datasetserial

Same substation and county

Maddox Creek substation: 4 requests in the PJM queue, 3 active totaling 113.2 MW.

Queue IDProjectMWResourceStatus
AE1-102Blue Creek Wind Farm15.6SolarEngineering and Procurement
AC2-044Blue Creek Wind Farm7.6SolarEngineering and Procurement
AB2-016Maddox Creek 345kV13WindWithdrawn

Van Wert, OH: 26 requests in the PJM queue, 6 active totaling 463.2 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy150
MW capacity90
MFO150

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.