Blue Creek Wind Farm
PJM queue ID AE1-102
Blue Creek Wind Farm (AE1-102) is listed in the PJM interconnection queue as a 15.6 MW solar project in Van Wert County, OH. The filing names Maddox Creek as its point of interconnection. PJM lists its status as “Engineering and Procurement”, with a target commercial operation date of September 9, 2027.
| Queue ID | AE1-102 |
|---|---|
| Project name | Blue Creek Wind Farm |
| Status (as published) | Engineering and Procurement |
| Substation | Maddox Creek |
| Point of interconnection | Maddox Creek 345 kV |
| County | Van Wert |
| State | OH |
| Voltage | 345 kV |
| Capacity | 15.6 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2027-09-09 |
| Source dataset | serial |
Same substation and county
Maddox Creek substation: 4 requests in the PJM queue, 3 active totaling 113.2 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| AF2-014 | Wild Grains Solar | 90 | Solar | Under Construction |
| AC2-044 | Blue Creek Wind Farm | 7.6 | Solar | Engineering and Procurement |
| AB2-016 | Maddox Creek 345kV | 13 | Wind | Withdrawn |
Van Wert, OH: 26 requests in the PJM queue, 6 active totaling 463.2 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 26 |
| MW capacity | 15.6 |
| MFO | 396 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.