King and Queen, VA interconnection queue
13 active projects totalling 210.7 MW in the PJM queue, plus 7 with terminal status (shown greyed).
13active projects
210.7active MW
20total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| C01-1364 | Dunbrooke - Lauraville 115 kV | 115 | 150 | Hybrid | Withdrawn |
| C01-1184 | Dunnsville - King and Queen 230 kV | 230 | 96.8 | Solar | Active |
| AI2-037 | Lauraville-Dunbrooke 115kV | 115 | 85 | Solar | Withdrawn |
| AH1-267 | Papermill IND – Harmony Village 230 kV | 230 | 72 | Solar | Withdrawn |
| AG1-183 | St. Johns DP-REC 115 kV | 115 | 35.5 | Solar | Withdrawn |
| AG2-124 | Shackleford-Harmony 115 kV | 115 | 33.3 | Solar | Active |
| AC1-065 | Walnut Solar I | 115 | 19 | Solar | Under Construction |
| AG1-187 | St. Johns DP-REC 115 kV | 115 | 14.5 | Battery | Withdrawn |
| AG2-607 | St. Johns - Dunbrook 34.5 kV | 34.5 | 12.7 | Solar | Withdrawn |
| Q70 | Brunswick | 34.5 | 11 | Gas | In Service |
| O62 | Shackleford 34.5kV | 34.5 | 8 | Gas | Withdrawn |
| AC2-110 | Walnut Solar I | 115 | 7.6 | Solar | Under Construction |
| AD2-039 | Walnut Solar I | 115 | 7.6 | Solar | Under Construction |
| AE1-004 | Walnut Solar I | 115 | 7.6 | Solar | Under Construction |
| AE2-005 | Walnut Solar I | 115 | 7.6 | Solar | Under Construction |
| AF1-014 | Walnut Solar I | 115 | 7.2 | Solar | Under Construction |
| W1-077 | King and Queen | 34.5 | 4 | Gas | In Service |
| C01-1896 | Bagby 12.47 kV | 12.5 | 3.8 | Solar | Active |
| AH1-397 | Shacklesfords 34.5 kV | 34.5 | 3 | Solar | Active |
| AC1-063 | King & Queen Landfill Facility | 34.5 | 2.2 | Gas | In Service |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.