Substation Scout

King and Queen, VA interconnection queue

12 active projects totalling 177.4 MW in the PJM queue, plus 8 with terminal status (shown greyed).

12active projects
177.4active MW
20total filed
Queue IDProjectkVMWResourceStatus
C01-1364 Dunbrooke - Lauraville 115 kV 115 150 Hybrid Withdrawn
C01-1184 Dunnsville - King and Queen 230 kV 230 96.8 Solar Active
AI2-037 Lauraville-Dunbrooke 115kV 115 85 Solar Withdrawn
AH1-267 Papermill IND – Harmony Village 230 kV 230 72 Solar Withdrawn
AG1-183 St. Johns DP-REC 115 kV 115 35.5 Solar Withdrawn
AG2-124 Shackleford-Harmony 115 kV 115 33.3 Solar Withdrawn
AC1-065 Walnut Solar I 115 19 Solar Partially in Service - Under Construction
AG1-187 St. Johns DP-REC 115 kV 115 14.5 Battery Withdrawn
AG2-607 St. Johns - Dunbrook 34.5 kV 34.5 12.7 Solar Withdrawn
Q70 Brunswick 34.5 11 Gas In Service
O62 Shackleford 34.5kV 34.5 8 Gas Withdrawn
AC2-110 Walnut Solar I 115 7.6 Solar Partially in Service - Under Construction
AD2-039 Walnut Solar I 115 7.6 Solar Partially in Service - Under Construction
AE1-004 Walnut Solar I 115 7.6 Solar Partially in Service - Under Construction
AE2-005 Walnut Solar I 115 7.6 Solar Partially in Service - Under Construction
AF1-014 Walnut Solar I 115 7.2 Solar Partially in Service - Under Construction
W1-077 King and Queen 34.5 4 Gas In Service
C01-1896 Bagby 12.47 kV 12.5 3.8 Solar Active
AH1-397 Shacklesfords 34.5 kV 34.5 3 Solar Active
AC1-063 King & Queen Landfill Facility 34.5 2.2 Gas In Service

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.