Shacklefords substation interconnection queue
2 active projects totaling 10.2 MW in the PJM queue.
2 PJM queue filings name Shacklefords as the point of interconnection, all in VA.
Target commercial operation dates as filed run from Oct 2009 to Dec 2011 (2 filings).
2active projects
10.2active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| T79 | Middle Pennisula Gas to Energy Power Plant | 34.5 | 6.2 | Gas | In Service | Oct 2009 |
| W1-077 | King and Queen | 34.5 | 4 | Gas | In Service | Dec 2011 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in Gloucester County, VA
- Harmony Village-Shackleford: 9 active, 146.6 MW of 11 filed
- Wan: 2 active, 25 MW of 2 filed
- White Marsh: 1 active, 12 MW of 3 filed
- Papermill Tap - Harmony Village: none active of 2 filed
Other PJM queue substations in King and Queen County, VA
- Harmony Village-Shackleford: 9 active, 146.6 MW of 11 filed
- Shackleford: 2 active, 12.2 MW of 3 filed
- Lawrenceville: 1 active, 11 MW of 3 filed
- St. Johns DP-REC: none active of 2 filed