Substation Scout

Kanawha River - Carbondale substation interconnection queue

2 active projects totaling 117.8 MW in the PJM queue, plus 1 with terminal status (shown grayed).

3 PJM queue filings name Kanawha River - Carbondale as the point of interconnection, all in WV.

Target commercial operation dates as filed run from Dec 2024 to Nov 2028 (3 filings). 2 active filings target a date after November 27, 2026.

Transmission owner as filed: AEP (2 filings).

2active projects
117.8active MW
3total filed
Queue IDProjectkVMWResourceStatusTarget COD
C01-1282 Kanawha River - Carbondale 138 kV 138 80 Battery Active Nov 2028
AG2-656 Kanawha River - Carbondale 138 kV 138 60 Solar Withdrawn Dec 2024
AG2-657 Kanawha River - Carbondale 138 kV 138 37.8 Solar Active Nov 2028

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Other PJM queue substations in Fayette County, WV

All 15 PJM queue filings in Fayette County, WV.

Other PJM queue substations in Kanawha County, WV

All 12 PJM queue filings in Kanawha County, WV.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →