Substation Scout

Kanawha River substation interconnection queue

1 active project totaling 30 MW in the PJM queue, plus 3 with terminal status (shown grayed).

4 PJM queue filings name Kanawha River as the point of interconnection, all in Fayette County, WV.

Target commercial operation dates as filed run from Jun 2013 to Sep 2029 (4 filings). 1 active filing targets a date after November 27, 2026.

1active projects
30active MW
4total filed
Queue IDProjectkVMWResourceStatusTarget COD
AE2-158 Kanawha River 138 kV 138 48 Hydro Withdrawn Oct 2021
AE2-160 Hawks Nest Hydro 138 30 Hydro Engineering and Procurement Sep 2029
W3-161 Kanawha River 138kV 138 13 Other Withdrawn Jun 2013
AE2-159 Kanawha River 138 kV 138 0 Hydro Withdrawn Oct 2021

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Other PJM queue substations in Fayette County, WV

All 15 PJM queue filings in Fayette County, WV.