Kanawha River substation interconnection queue
1 active project totaling 30 MW in the PJM queue, plus 3 with terminal status (shown grayed).
4 PJM queue filings name Kanawha River as the point of interconnection, all in Fayette County, WV.
Target commercial operation dates as filed run from Jun 2013 to Sep 2029 (4 filings). 1 active filing targets a date after November 27, 2026.
1active projects
30active MW
4total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| AE2-158 | Kanawha River 138 kV | 138 | 48 | Hydro | Withdrawn | Oct 2021 |
| AE2-160 | Hawks Nest Hydro | 138 | 30 | Hydro | Engineering and Procurement | Sep 2029 |
| W3-161 | Kanawha River 138kV | 138 | 13 | Other | Withdrawn | Jun 2013 |
| AE2-159 | Kanawha River 138 kV | 138 | 0 | Hydro | Withdrawn | Oct 2021 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in Fayette County, WV
- Kanawha River - Carbondale: 2 active, 117.8 MW of 3 filed
- Kanawha: 1 active, 5.5 MW of 3 filed
- Carbondale: none active of 2 filed
- Layland: none active of 2 filed
- Nuttall: none active of 2 filed
Site Scanner