Substation Scout

Kanawha River substation interconnection queue

1 active project totalling 30 MW in the PJM queue, plus 3 with terminal status (shown greyed).

1active projects
30active MW
4total filed
Queue IDProjectkVMWResourceStatus
AE2-158 Kanawha River 138 kV 138 48 Hydro Withdrawn
AE2-160 Hawks Nest Hydro 138 30 Hydro Engineering and Procurement
W3-161 Kanawha River 138kV 138 13 Other Withdrawn
AE2-159 Kanawha River 138 kV 138 0 Hydro Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.