Kanawha, WV interconnection queue

4 active projects totalling 13.2 MW in the PJM queue, plus 8 with terminal status (shown greyed).

4active projects
13.2active MW
12total filed
Queue IDProjectkVMWResourceStatus
AH2-043 Cabin Creek 138 kV 138 140 Hybrid Withdrawn
AH2-278 Cabin Creek 138 kV 138 100 Battery Withdrawn
AH1-426 Gilboa-Jones Branch 138 kV IV 138 64.6 Battery Withdrawn
AH2-209 Cabin Creek 138 kV 138 63 Hybrid Withdrawn
AG2-656 Kanawha River - Carbondale 138 kV 138 60 Solar Withdrawn
O37 Belle 46kV 46 14 Gas Withdrawn
AD1-149 Carbondale 69 kV 69 8.3 Hybrid Withdrawn
R82 Kanawna River #1 n/r 5 Coal In Service
R83 Kanawna River #2 n/r 5 Coal In Service
Y3-025 Charleston Clean Energy 12 3.2 Gas In Service
AH2-134 TBD 34.5 kV 34.5 0 Solar Withdrawn
V1-023 Charlston LF 12 0 Gas In Service

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.