Farmers Valley-Ridgeway substation interconnection queue
1 active project totaling 61.9 MW in the PJM queue, plus 1 with terminal status (shown grayed).
2 PJM queue filings name Farmers Valley-Ridgeway as the point of interconnection, all in McKean County, PA.
Target commercial operation dates as filed run from Jun 2023 to Aug 2026 (2 filings).
1active projects
61.9active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| AE2-113 | Clermont Solar | 115 | 61.9 | Solar | Under Construction | Aug 2026 |
| AF2-052 | Farmers Valley-Ridgeway 115 kV | 115 | 37 | Solar | Withdrawn | Jun 2023 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Same name on other Substation Scout pages
Other sources that print a substation named “Farmers Valley-Ridgeway” in PA. They are matched by name and state only, so a page listed here may describe a different substation with the same name. Check the location and utility on each.
- Farmers Valley - Ridgeway: PJM interconnection queue (PA)
Other PJM queue substations in McKean County, PA
- Bradford: 1 active, 1.5 MW of 2 filed
- Pierce Brook - Lewis Run: none active of 4 filed
- East Towanda-Grover: none active of 3 filed
- Lewis Run-Pierce Brook: none active of 3 filed
- Pierce Brook-Lewis Run: none active of 3 filed
- Farmers Valley - Ridgeway: none active of 2 filed
- Lewis Run - Pierce Brook: none active of 2 filed