Farmers Valley-Ridgeway substation interconnection queue

1 active project totalling 61.9 MW in the PJM queue, plus 1 with terminal status (shown greyed).

1active projects
61.9active MW
2total filed
Queue IDProjectkVMWResourceStatus
AE2-113 Clermont Solar 115 61.9 Solar Under Construction
AF2-052 Farmers Valley-Ridgeway 115 kV 115 37 Solar Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.