Dequine - Eugene substation interconnection queue

2 active projects totalling 490.5 MW in the PJM queue, plus 4 with terminal status (shown greyed).

2active projects
490.5active MW
6total filed
Queue IDProjectkVMWResourceStatus
C01-2193 Dequine - Eugene 345 kV 345 250 Battery Active
C01-2192 Dequine - Eugene 345 kV 345 240.5 Solar Active
AH2-257 Dequine - Eugene 345 kV 345 240 Solar Withdrawn
AG2-454 Dequine - Eugene 345 kV 345 210 Solar Withdrawn
AH1-502 Dequine - Eugene 345 kV 345 150 Battery Withdrawn
AI2-147 Dequine - Eugene 345 kV 345 78 Wind Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.