Substation Scout

Dolphin Solar

PJM queue ID AG1-226

Dolphin Solar (AG1-226) is listed in the PJM interconnection queue as a 142 MW solar project in Fountain County, IN. The filing names Dequine-Eugene as its point of interconnection. PJM lists its status as “EP”, with a target commercial operation date of March 31, 2029.

Queue IDAG1-226
Project nameDolphin Solar
Status (as published)EP
SubstationDequine-Eugene
Point of interconnectionDequine-Eugene 345 kV
CountyFountain
StateIN
Voltage345 kV
Capacity142 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Target commercial operation2029-03-31
Source datasetcycle

Same substation and county

Dequine-Eugene substation: 4 requests in the PJM queue, 3 active totaling 203 MW.

Queue IDProjectMWResourceStatus
AG2-163Dequine-Eugene 345 kV35SolarActive
AG1-237Warren County Wind Energy Center26WindEngineering and Procurement
U1-024Dequine-Eugene 345kV65WindWithdrawn

Fountain, IN: 10 requests in the PJM queue, 4 active totaling 294 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

DeveloperDolphin Solar LLC
Transmission ownerAEP
Project typeGeneration Interconnection
CycleTC1
StageFINAL AGREEMENT
MW energy450.0
MW capacity142.0
MFO450.0
Submitted date9/24/2020
Last updated3/4/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first