Dequine - Sullivan substation interconnection queue
2 active projects totaling 882.9 MW in the PJM queue, plus 1 with terminal status (shown grayed).
3 PJM queue filings name Dequine - Sullivan as the point of interconnection, all in IN.
Target commercial operation dates as filed run from Mar 2024 to May 2030 (3 filings). 2 active filings target a date after November 27, 2026.
Transmission owner as filed: AEP (3 filings).
2active projects
882.9active MW
3total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| C01-2191 | Dequine - Sullivan 345 kV | 345 | 450 | Battery | Active | May 2030 |
| C01-2190 | Dequine - Sullivan 345 kV | 345 | 432.9 | Solar | Active | May 2030 |
| AG2-455 | Dequine - Sullivan 345 kV | 345 | 196 | Solar | Withdrawn | Mar 2024 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in Vigo County, IN
- Sullivan - Dequine: none active of 4 filed
Other PJM queue substations in Fountain County, IN
- Dequine-Eugene: 3 active, 203 MW of 4 filed
- Eugene - Dequine: 2 active, 117 MW of 5 filed
- Dequine - Eugene: none active of 6 filed