Substation Scout

Deer Creek-Fisher Body-Mullin substation interconnection queue

1 active project totaling 26 MW in the PJM queue, plus 2 with terminal status (shown grayed).

3 PJM queue filings name Deer Creek-Fisher Body-Mullin as the point of interconnection, all in IN.

Target commercial operation dates as filed run from Dec 2012 to Sep 2021 (3 filings).

1active projects
26active MW
3total filed
Queue IDProjectkVMWResourceStatusTarget COD
AI2-492 Deer Creek-Fisher Body-Mullin 138kV 138 106.4 Wind Withdrawn Dec 2012
U3-002 Wildcat Wind Farm I 138 26 Wind In Service Dec 2012
AF1-080 Deer Creek-Fisher Body-Mullin 138 kV 138 20 Battery Withdrawn Sep 2021

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Other PJM queue substations in Grant County, IN

All 15 PJM queue filings in Grant County, IN.

Other PJM queue substations in Madison County, IN

All 17 PJM queue filings in Madison County, IN.