Deer Creek-Fisher Body-Mullin substation interconnection queue

1 active project totalling 26 MW in the PJM queue, plus 2 with terminal status (shown greyed).

1active projects
26active MW
3total filed
Queue IDProjectkVMWResourceStatus
AI2-492 Deer Creek-Fisher Body-Mullin 138kV 138 106.4 Wind Withdrawn
U3-002 Wildcat Wind Farm I 138 26 Wind In Service
AF1-080 Deer Creek-Fisher Body-Mullin 138 kV 138 20 Battery Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.