Substation Scout

Mississinewa-Gaston substation interconnection queue

3 active projects totalling 136 MW in the PJM queue.

3active projects
136active MW
3total filed
Queue IDProjectkVMWResourceStatus
AE1-207 Golden Aster Solar Energy Center 138 67.2 Solar Suspended
AE2-172 Golden Aster Solar Energy Center 138 40 Battery Suspended
AH1-306 Mississinewa-Gaston 138 kV 138 28.8 Solar Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.