Substation Scout

Mississinewa-Gaston substation interconnection queue

3 active projects totaling 136 MW in the PJM queue.

3 PJM queue filings name Mississinewa-Gaston as the point of interconnection, all in Grant County, IN.

Target commercial operation dates as filed run from May 2026 to Dec 2030 (3 filings). 1 active filing targets a date after November 27, 2026.

Transmission owner as filed: AEP (1 filing).

3active projects
136active MW
3total filed
Queue IDProjectkVMWResourceStatusTarget COD
AE1-207 Golden Aster Solar Energy Center 138 67.2 Solar Suspended May 2026
AE2-172 Golden Aster Solar Energy Center 138 40 Battery Suspended May 2026
AH1-306 Mississinewa-Gaston 138 kV 138 28.8 Solar Active Dec 2030

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Other PJM queue substations in Grant County, IN

All 15 PJM queue filings in Grant County, IN.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first