Cunningham - Elmont substation interconnection queue
2 active projects totaling 3,238 MW in the PJM queue, plus 1 with terminal status (shown grayed).
3 PJM queue filings name Cunningham - Elmont as the point of interconnection, all in VA.
Target commercial operation dates as filed run from Jun 2026 to Dec 2030 (3 filings). 1 active filing targets a date after November 27, 2026.
Transmission owner as filed: Dominion (2 filings).
2active projects
3,238active MW
3total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| C01-1111 | Cunningham - Elmont 500 kV | 500 | 1,619 | Gas | Active | Dec 2030 |
| C01-1112 | Cunningham - Elmont 500 kV | 500 | 1,619 | Gas | Active | Jun 2026 |
| AH1-018 | Cunningham - Elmont 500 kV | 500 | 89 | Solar | Withdrawn | Jun 2026 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in Cumberland County, VA
- Cobbs Creek - James River Industrial: 1 active, 45 MW of 2 filed
- Buckingham- Farmville: none active of 4 filed
- Cartersville: none active of 2 filed
Other PJM queue substations in Fluvanna County, VA
- Bremo: 3 active, 2,185 MW of 4 filed
- Cunningham: 6 active, 1,704.6 MW of 7 filed
- Bremo-Kidds Store: none active of 2 filed
- Fork Union: none active of 2 filed
- Kidds Store - Fork Union II: none active of 2 filed
- Shockoe DP-Chatham: none active of 2 filed