Cunningham - Elmont substation interconnection queue

2 active projects totaling 3,238 MW in the PJM queue, plus 1 with terminal status (shown grayed).

3 PJM queue filings name Cunningham - Elmont as the point of interconnection, all in VA.

Target commercial operation dates as filed run from Jun 2026 to Dec 2030 (3 filings). 1 active filing targets a date after November 27, 2026.

Transmission owner as filed: Dominion (2 filings).

2active projects
3,238active MW
3total filed
Queue IDProjectkVMWResourceStatusTarget COD
C01-1111 Cunningham - Elmont 500 kV 500 1,619 Gas Active Dec 2030
C01-1112 Cunningham - Elmont 500 kV 500 1,619 Gas Active Jun 2026
AH1-018 Cunningham - Elmont 500 kV 500 89 Solar Withdrawn Jun 2026

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Other PJM queue substations in Cumberland County, VA

All 16 PJM queue filings in Cumberland County, VA.

Other PJM queue substations in Fluvanna County, VA

All 31 PJM queue filings in Fluvanna County, VA.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first