Cunningham - Elmont substation interconnection queue

2 active projects totalling 3,238 MW in the PJM queue, plus 1 with terminal status (shown greyed).

2active projects
3,238active MW
3total filed
Queue IDProjectkVMWResourceStatus
C01-1111 Cunningham - Elmont 500 kV 500 1,619 Gas Active
C01-1112 Cunningham - Elmont 500 kV 500 1,619 Gas Active
AH1-018 Cunningham - Elmont 500 kV 500 89 Solar Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.