Substation Scout

Cobbs Creek - James River Industrial substation interconnection queue

1 active project totalling 45 MW in the PJM queue, plus 1 with terminal status (shown greyed).

1active projects
45active MW
2total filed
Queue IDProjectkVMWResourceStatus
AH1-241 Energix Westmoreland LLC 115 60 Solar Withdrawn
C01-1670 Cobbs Creek - James River Industrial 115 kV 115 45 Solar Active

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.