Cumberland, VA interconnection queue

6 active projects totalling 3,463 MW in the PJM queue, plus 10 with terminal status (shown greyed).

6active projects
3,463active MW
16total filed
Queue IDProjectkVMWResourceStatus
C01-1111 Cunningham - Elmont 500 kV 500 1,619 Gas Active
C01-1112 Cunningham - Elmont 500 kV 500 1,619 Gas Active
AH2-350 Cartersville 230kV 230 90 Solar Withdrawn
AG2-188 Farmville - Buckingham 230 kV 230 89 Solar Withdrawn
AG2-583 Bremo - Cartersville 230 kV 230 69 Solar Active
AG2-151 Trices Lake - James River Tap 115 kV 115 60 Solar Active
AH1-241 Energix Westmoreland LLC 115 60 Solar Withdrawn
AH1-439 ACE Development Company, LLC 230 51 Solar Active
C01-1670 Cobbs Creek - James River Industrial 115 kV 115 45 Solar Active
AH2-104 Willis Mts- Farmville 115kV 115 39.2 Hybrid Withdrawn
AH1-440 ACE Development Company, LLC 230 34 Battery Withdrawn
AI1-011 Buckingham- Farmville 230kV 230 27.6 Solar Withdrawn
AH1-374 Bremo-Cartersville 230 kV II 230 20 Battery Withdrawn
AI1-012 Buckingham- Farmville 230kV 230 18.4 Battery Withdrawn
AH2-013 Cartersville 34.5 kV 34.5 16 Hybrid Withdrawn
AI1-126 Farmville 12.47kV 12.5 6 Solar Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.