Cartersville substation interconnection queue

0 active projects totaling 0 MW in the PJM queue, plus 2 with terminal status (shown grayed).

2 PJM queue filings name Cartersville as the point of interconnection, all in Cumberland County, VA.

Target commercial operation dates as filed run from Dec 2022 to Dec 2025 (2 filings).

0active projects
0active MW
2total filed
Queue IDProjectkVMWResourceStatusTarget COD
AH2-350 Cartersville 230kV 230 90 Solar Withdrawn Dec 2025
AH2-013 Cartersville 34.5 kV 34.5 16 Hybrid Withdrawn Dec 2022

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Other PJM queue substations in Cumberland County, VA

All 16 PJM queue filings in Cumberland County, VA.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first