Pondtown Solar 2
PJM queue ID AB2-153
| Queue ID | AB2-153 |
|---|---|
| Project name | Pondtown Solar 2 |
| Status (as published) | In Service |
| Substation | Church-Wye Mills |
| Point of interconnection | Church-Wye Mills 138 kV |
| County | Queen Anne's |
| State | MD |
| Voltage | 138 kV |
| Capacity | 7.6 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalised for filtering) |
| Target commercial operation | 2023-12-31 |
| Source dataset | serial |
Additional filed fields
| Project Type | Generation Interconnection |
|---|---|
| Mw Energy | 20 |
| Mw Capacity | 7.6 |
| Mfo | 40 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.