Boykins substation interconnection queue

1 active project totalling 100 MW in the PJM queue, plus 7 with terminal status (shown greyed).

1active projects
100active MW
8total filed
Queue IDProjectkVMWResourceStatus
C01-2007 Boykins 115 kV 115 100 Battery Active
AD2-208 Boykins 115 kV 115 60 Solar Withdrawn
AB1-054 Boykins 115kV 115 40.2 Solar Withdrawn
AB1-028 Boykins 34.5kV 34.5 14 Solar Withdrawn
AA2-087 Boykins 34.5kV 34.5 7.6 Solar Withdrawn
Z2-099 Boykins Solar 34.5 5.9 Solar Withdrawn
AG1-394 SH-Mehrrin Solar 34.5 5 Solar Withdrawn
AA2-086 Boykins Solar 34.5 3.1 Solar Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.