Gosport substation interconnection queue

0 active projects totalling 0 MW in the PJM queue, plus 5 with terminal status (shown greyed).

0active projects
0active MW
5total filed
Queue IDProjectkVMWResourceStatus
Y2-001 SPSA Navy Power Plant n/r 40 Other Deactivated
Q32 Gosport 115 30 Other Withdrawn
AE1-152 Gosport 34.5 kV 34.5 20.2 Hybrid Withdrawn
Q64 Gosport 115kV 115 20 Other Withdrawn
T104 SPSA Navy Power Plant 115 20 Other Deactivated

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.