City of Portsmouth, VA interconnection queue

0 active projects totalling 0 MW in the PJM queue, plus 6 with terminal status (shown greyed).

0active projects
0active MW
6total filed
Queue IDProjectkVMWResourceStatus
AD2-208 Boykins 115 kV 115 60 Solar Withdrawn
Y2-001 SPSA Navy Power Plant n/r 40 Other Deactivated
Q32 Gosport 115 30 Other Withdrawn
AE1-152 Gosport 34.5 kV 34.5 20.2 Hybrid Withdrawn
Q64 Gosport 115kV 115 20 Other Withdrawn
T104 SPSA Navy Power Plant 115 20 Other Deactivated

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.