Substation Scout

Riley Substation (#); AEP substation interconnection queue

3 active projects totalling 932 MW in the ERCOT queue.

3active projects
932active MW
3total filed
Queue IDProjectkVMWResourceStatus
27INR0005 Dundee East A Wind 345 524 Wind SS Completed, FIS Started, IA
27INR0011 Dundee East B Wind 345 261.5 Wind SS Completed, FIS Started, IA
27INR0004 Dundee West Wind 345 146.5 Wind SS Completed, FIS Started, IA

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.