Dundee East A Wind (27INR0005) is listed in the ERCOT interconnection queue as a 524 MW wind project in Baylor County, TX. The filing names Riley Substation (#); AEP as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, IA”, with a target commercial operation date of December 31, 2027. It records the screening study as complete on March 30, 2023 and the interconnection agreement as signed on February 21, 2025.

Queue ID27INR0005
Project nameDundee East A Wind
Status (as published)SS Completed, FIS Started, IA
SubstationRiley Substation (#); AEP
Point of interconnection345 kV Riley Substation (#6101); AEP
CountyBaylor
StateTX
Voltage345 kV
Capacity524 MW
Resource (as published)WIN/WT
Resource categoryWind (normalized for filtering)
Target commercial operation2027-12-31
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Riley Substation (#); AEP substation: 3 requests in the ERCOT queue, 3 active totaling 932 MW.

Queue IDProjectMWResourceStatus
27INR0011Dundee East B Wind261.5WindSS Completed, FIS Started, IA
27INR0004Dundee West Wind146.5WindSS Completed, FIS Started, IA

Baylor, TX: 7 requests in the ERCOT queue, 6 active totaling 1,891 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityFelix 2, LLC
CDR reporting zoneWEST
Fuel codeWIN
Technology codeWT
Interconnection agreement signed2025-02-21
Screening study complete2023-03-30
Air permitNot Required
Water availabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first