Riley substation interconnection queue

3 active projects totaling 1,042.5 MW in the ERCOT queue.

3 ERCOT queue filings name Riley as the point of interconnection, all in Wilbarger County, TX.

Target commercial operation dates as filed run from Jun 2028 to Oct 2029 (3 filings). 3 active filings target a date after November 27, 2026.

Interconnecting entity as filed: Oklaunion Power Station, LLC (1 filing), Felix 1, LLC (1 filing), Crescent Solar, LLC (1 filing).

3active projects
1,042.5active MW
3total filed
Queue IDProjectkVMWResourceStatusTarget COD
22INR0497 TEXPO 345 680 Gas SS Completed, FIS Started, No IA Oct 2029
27INR0012 Felix West Solar 345 185 Solar SS Completed, FIS Started, IA Jun 2028
22INR0209 Felix North Solar 345 177.5 Solar SS Completed, FIS Started, IA Jun 2028

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.

Tracked changes at this substation

2 changes to filings at this point of interconnection, observed between weekly snapshots of the ERCOT queue. For a capacity revision MW is the change, not the new total.

DetectedQueue IDChangeMWStatus was → now
2026-11-0927INR0012Capacity revised−16 SS Completed, FIS Started, IA → SS Completed, FIS Started, IA
2026-11-0922INR0209Capacity revised−23.5 SS Completed, FIS Started, IA → SS Completed, FIS Started, IA

Same name on other Substation Scout pages

Other sources that print a substation named “Riley” in TX. They are matched by name and state only, so a page listed here may describe a different substation with the same name. Check the location and utility on each.

Other ERCOT queue substations in Wilbarger County, TX

All 24 ERCOT queue filings in Wilbarger County, TX.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first