Riley substation interconnection queue
3 active projects totalling 1,082 MW in the ERCOT queue.
3active projects
1,082active MW
3total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| 22INR0497 | TEXPO | 345 | 680 | Gas | SS Completed, FIS Started, No IA |
| 22INR0209 | Felix North Solar | 345 | 201 | Solar | SS Completed, FIS Started, IA |
| 27INR0012 | Felix West Solar | 345 | 201 | Solar | SS Completed, FIS Started, IA |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.