Bailey substation interconnection queue
3 active projects totalling 707.8 MW in the ERCOT queue.
3active projects
707.8active MW
3total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| 29INR0082 | Peach Creek Solar | 345 | 300 | Solar | SS Completed, FIS Started, No IA |
| 23INR0058 | Erin Solar | 345 | 208.3 | Solar | SS Completed, FIS Started, IA |
| 22INR0517 | Lane City Wind | 345 | 199.5 | Wind | SS Completed, FIS Completed, IA |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.