Home / ERCOT / substation / tap Blue – Hillje Ckt.#27
tap Blue – Hillje Ckt.#27 substation interconnection queue
3 active projects
totalling 660.6 MW in the ERCOT queue.
3 active projects
660.6 active MW
3 total filed
Queue ID Project kV MW Resource Status
21INR0220
Maleza Solar
345
254.9
Solar
SS Completed, FIS Not Started, IA
23INR0227
Maleza Solar II
345
254.9
Solar
SS Completed, FIS Started, No IA
21INR0456
Maleza Storage
345
150.8
Battery
SS Completed, FIS Started, No IA
A request with terminal status left the queue as filed.
That is a record of the filing, not evidence of injection capacity at this location.
Confirm deliverability with ERCOT before relying on these figures.
Site Scanner draws on HIFLD substations and electric retail service
territories, USGS watershed boundaries, FEMA flood hazard layers and US Census
geocoding. Queue data is compiled from public interconnection
queue filings. Every figure carries its source and retrieval date.
A withdrawal records that a request left the queue. It says
nothing about injection capacity at that location. Verify with the relevant ISO before
relying on any figure. Queue datasets are tracked separately and are
not directly comparable: status vocabularies, fuel coding, and publication
cadence all differ.
Screening aid only. Not a system impact study. Contiguous US.