Bailey

Named in 3 listed projects in ERCOT’s transmission project tracking workbook, in Wharton County. First named in the release with data as of June 1, 2016.

Whartoncounty as printed
345kV
CNPutility
3projects listed

Expansion at an existing substation: new or expanded yard. The quoted wording describes a new or expanded yard, bus, bay or station at this substation. “Expand 345kV Bailey substation” — project 69890, as the utility reported it

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Wharton, TX: ERCOT queue, 42 active of 44. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
This models the new CEHE Raider Substation and upgrades required for a proposed load addition
Install new 345kV CEHE Raider substation. Loop 345 kV Ckt. 72 Bailey-Cedar Creek line into the new 345 kV Raider substation. Upgrade line relaying on Ckt 72 Cedar Creek-Raider-Bailey. Remove temporary 138 kV service.
ERCOT project 110068A
CNP
Tier 4
Planned
Future tab
345 May 2027 Raider to Cedar Creek/Bailey
Wharton County
Raider, Cedar Creek, Bailey
Bailey 345kV Substation Expansion for Ray Gulf Wind (22INR0517)
Expand 345kV Bailey substation for Ray Gulf Wind generator interconnection (22INR0517)
ERCOT project 69890
CNP
Tier 4
In-Service
Completed tab
345 Mar 2025
actual 2025-07
Bailey
Wharton County
Bailey
Facility Ratings Methodology Phase 2 (FRM2) Upgrades
Upgrade Ckt.62A Bailey to Waterhole to increase thermal limits as part of FRM2 upgrades.
ERCOT project 99453R
CNP
Tier 4
Planned
Current-year planned tab
345 Oct 2026 Bailey to Waterhole
Wharton County
Bailey, Waterhole

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 2026110068AMoved between tabsCurrent-year planned → Future
October 1, 2026110068AStatus as reportedConceptual → Planned
October 1, 2026110068AProjected in-service dateOct 2026 → May 2027
July 13, 2026110068AFirst listedon the Current-year planned tab
February 1, 202699453RMoved between tabsFuture → Current-year planned
October 1, 202569890Status as reportedPlanned → In-Service
October 1, 202599453RFirst listedon the Future tab
June 1, 202569890Moved between tabsFuture → Completed
June 1, 202569890Projected in-service dateFeb 2025 → Mar 2025
February 1, 202569890Projected in-service dateSep 2025 → Feb 2025

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.