Substation Scout

Gulftie substation interconnection queue

2 active projects totaling 416.1 MW in the ERCOT queue.

2 ERCOT queue filings name Gulftie as the point of interconnection, all in Wharton County, TX.

Target commercial operation dates as filed run from Mar 2025 to Dec 2028 (2 filings). 1 active filing targets a date after November 27, 2026.

Interconnecting entity as filed: Boling Generation (1 filing), Wharton County Generation, LLC (1 filing).

2active projects
416.1active MW
2total filed
Queue IDProjectkVMWResourceStatusTarget COD
24INR0576 Boling Generation (TEF-Due Diligience) 138 400 Gas SS Completed, FIS Completed, No IA Dec 2028
24INR0605 TEXAS GULF SULPHUR REPOWER 138 16.1 Gas SS Completed, FIS Completed, IA Mar 2025

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.

Other ERCOT queue substations in Wharton County, TX

All 44 ERCOT queue filings in Wharton County, TX.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first