Rock Creek Substation substation interconnection queue

5 active projects totalling 725 MW in the BPA queue, plus 1 with terminal status (shown greyed).

5active projects
725active MW
6total filed
Queue IDProjectkVMWResourceStatus
G0222 Windy Flats -Dooley Wind n/r 250 Wind ENERGIZED
G0979 Not reported n/r 200 Solar STUDY
G0233 Not reported n/r 150 Wind WITHDRAWN
G0936 Not reported n/r 150 Wind STUDY COMPLETED
G0208 Tuolumne Wind (Windy Point 1) 230 125 Wind ENERGIZED
G0717 Not reported n/r 0 Battery STUDY COMPLETED

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with BPA before relying on these figures.