Substation Scout

Tuolumne Wind (Windy Point 1)

BPA queue ID G0208

Queue IDG0208
Project nameTuolumne Wind (Windy Point 1)
Status (as published)ENERGIZED
SubstationRock Creek Substation
Point of interconnectionRock Creek Substation 230 kV
CountyKlickitat
StateWA
Voltage230 kV
Capacity125 MW
Resource (as published)Wind Turbine/Wind Turbine
Resource categoryWind (normalised for filtering)
Target commercial operation2007-03-01
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

RequestorWindy Point Partners, LLC
Connection TypeGI
Interconnection TypeNRIS
PoiRock Creek Substation 230 kV
Generator TypeWind Turbine
Fuel SourceWind Turbine
Nameplate Mw Total125
Max Summer Mw125
Max Winter Mw125
Reason Not Completed.
Commentson-line December 2008(sold to Turlock Irrigation District, operated as Tuolumne Wind)

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.