Substation Scout

Not reported

BPA queue ID G0867

Queue IDG0867
Project nameNot reported
Status (as published)STUDY
SubstationTBD
Point of interconnectionTBD
CountySherman
StateOR
VoltageNot reported
Capacity100 MW
Resource (as published)Wind Turbine/Wind Turbine
Resource categoryWind (normalised for filtering)
Target commercial operation2027-12-01
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

Connection TypeGI
Interconnection TypeNRIS & ERIS
PoiTBD
Generator TypeWind Turbine
Fuel SourceWind Turbine
Nameplate Mw Total102
Max Summer Mw100
Max Winter Mw100
ClusterTransition Cluster
Reason Not Completed.
CommentsRosebush Substation 230 kV LowerC1 Study Area

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.