G0827 Klondike Wind
BPA queue ID G0827
| Queue ID | G0827 |
|---|---|
| Project name | G0827 Klondike Wind |
| Status (as published) | ENERGIZED |
| Substation | John Day – Klondike Schoolhouse No 1 Line |
| Point of interconnection | John Day – Klondike Schoolhouse 230 kV No 1 Line |
| County | Sherman |
| State | OR |
| Voltage | 230 kV |
| Capacity | 25 MW |
| Resource (as published) | Wind Turbine/Wind Turbine |
| Resource category | Wind (normalised for filtering) |
| Target commercial operation | 2024-12-16 |
| Source dataset | bpa-generation |
Tracked changes
No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →
Additional filed fields
| Requestor | Klondike Wind Power, LLC |
|---|---|
| Connection Type | GI |
| Interconnection Type | NRIS & ERIS |
| Poi | John Day – Klondike Schoolhouse 230 kV No 1 Line |
| Generator Type | Wind Turbine |
| Fuel Source | Wind Turbine |
| Nameplate Mw Total | 25 |
| Max Summer Mw | 25 |
| Max Winter Mw | 25 |
| Reason Not Completed | . |