Biglow Canyon Wind Farm Addition
BPA queue ID G0297
| Queue ID | G0297 |
|---|---|
| Project name | Biglow Canyon Wind Farm Addition |
| Status (as published) | ENERGIZED |
| Substation | Not reported |
| Point of interconnection | Not reported |
| County | Sherman |
| State | OR |
| Voltage | Not reported |
| Capacity | 50 MW |
| Resource (as published) | Wind Turbine/Wind Turbine |
| Resource category | Wind (normalised for filtering) |
| Target commercial operation | 2009-10-01 |
| Source dataset | bpa-generation |
Tracked changes
No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →
Additional filed fields
| Requestor | Portland General Electric Company |
|---|---|
| Connection Type | GI |
| Interconnection Type | ERIS |
| Generator Type | Wind Turbine |
| Fuel Source | Wind Turbine |
| Nameplate Mw Total | 50 |
| Max Summer Mw | 50 |
| Max Winter Mw | 50 |
| Reason Not Completed | . |
| Comments | on-line May 2010 (combined with Phase 3 of G099 for 125 MW) |