Hay Canyon/Star Point

BPA queue ID G0223

Queue IDG0223
Project nameHay Canyon/Star Point
Status (as published)ENERGIZED
SubstationJohn Day substation
Point of interconnectionJohn Day substation
CountySherman
StateOR
VoltageNot reported
Capacity201 MW
Resource (as published)Wind Turbine/Wind Turbine
Resource categoryWind (normalised for filtering)
Target commercial operation2008-12-01
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

RequestorAvangrid Power, LLC
Connection TypeGI
Interconnection TypeNRIS
PoiJohn Day substation
Generator TypeWind Turbine
Fuel SourceWind Turbine
Nameplate Mw Total201
Max Summer Mw201
Max Winter Mw201
Reason Not Completed.
CommentsHay Canyon on-line December 2008 for 101 MW; Star Point on-line January 2010. Two LGIAs provided.