TMI
Named in 1 PJM planning document for 1 project, on December 5, 2023.
Same name on other Substation Scout pages
Other sources that print a substation named “TMI”. They are matched by name and state only, so a page listed here may describe a different substation with the same name. Check the location and utility on each. Where a PJM planning record prints no state, the match is by name within the states the utility zone serves, which is weaker.
Projects naming this substation
Figures are from the most recent document naming each project, as printed. Each links to its page.
Part of a named transmission project: Maryland Piedmont Reliability Project (MPRP): Chanceford - Doubs 500 kV ($447.5M (PSEG)).
| Project | Status as printed | Cost estimate | In-service date | Customer load | As of |
|---|---|---|---|---|---|
| Recommended Solutions to Address Clusters - East B3800.1 –B3800.6 |
Not printed | $134.2 M | 6/1/2027 | Not printed | 2023-12-05 TEAC |
Other substations in this project
“Recommended Solutions to Address Clusters - East” also names 9 other substations, with what the most recent document says about each.
- Chanceford PPL New — “Build new Otter Creek 500 kV (Chanceford) Switching Station” (p. 18)
- Conastone PPL Work described at it — “Rebuild the existing Otter Creek - Conastone 230 kV line to become a double-circuit 500 kV line, operate Conastone circuit at 230 kV initially” (p. 18)
- Conastone PJM system-wide Work described at it — “towards Conastone station fence” (p. 57)
- Doubs PPL Not stated
- Otter Creek PPL New — “Build new Otter Creek 500 kV (Chanceford) Switching Station” (p. 18)
- Otter Creek PJM system-wide New — “Build New Otter Creek 500 kV switching station” (p. 57)
- Peach Bottom PPL Work described at it — “from the existing TMI-Peach Bottom 500 kV right-of-way” (p. 18)
- Peach Bottom PJM system-wide Work described at it — “Upgrade relay/terminal equipment at Peach Bottom and TMI substations” (p. 57)
- TMI PPL, PA Work described at it — “from the existing TMI-Peach Bottom 500 kV right-of-way” (p. 18)
Changes between documents
Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.
| What changed | Printed values | Earlier | Later |
|---|---|---|---|
| Cost estimate | $134.2 M → $148.15 M | 2023-12-05 | 2025-07-08 |
| Cost estimate prior value printed on the same page |
$148.15M → $148.15 M | 2025-07-08 | 2025-07-08 |
| Substations named | CONASTONE; OTTER CREEK; PEACH BOTTOM; TMI → CHANCEFORD; CONASTONE; DOUBS; OTTER CREEK; PEACH BOTTOM; TMI | 2023-12-05 | 2025-07-08 |
Every mention
| Date | Document | Project | What the document says about it |
|---|---|---|---|
| 2023-12-05 | TEAC Item 15 - Reliability Analysis Update 2022 Window 3 p. 57 |
Recommended Solutions to Address Clusters - East | “Upgrade relay/terminal equipment at Peach Bottom and TMI substations” 500 kV |
* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.
Before relying on any of this
- Names are machine-extracted from PDFs by a language model. Every exported name was checked to be printed in the PDF text; names read only from maps or diagrams are excluded.
- An entry is a name within a transmission zone, not a verified physical facility. The same name in two zones is two entries; spelling variants are merged only when they differ by punctuation, case or a generic suffix such as "Substation", or when a PJM document prints a rename for the same project (src/ingest/rtepAliases.json; the entry lists its old names).
- role is "new" only where a cited document phrase calls the substation new, describes constructing it, or calls it proposed (graded by src/lib/roleBasis.js), "existing" where a phrase describes work at it, otherwise "unknown".
- expansion is set on a substation that is not "new" where a cited phrase describes a new voltage level, a new or expanded yard, bus or bay, or a named load connected to it (graded by src/lib/expansionBasis.js). It reproduces what the document describes and adds nothing to it.
- Costs, dates, statuses and loads are the documents' own printed values for the most recent document that names the substation. Each one shipped here is printed on its cited page ("verification": "exact" or "on-page"); values that failed that check are withheld and counted in figures_withheld_unverified. None has been reviewed by a person.
- Zone is the transmission owner whose deck presented the project. PJM-SYSTEM marks names from PJM's own reliability decks, which span zones.
- A printed customer load is the amount a document states for a request. It says nothing about the substation's capability.