Substation Scout

Gore Substation

Named in 3 PJM planning documents for 1 project, from August 15, 2025 to October 6, 2026.

Existingdescribed as
APSzone
138 kVkV as printed
3mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Gore - Hampshire 138 kV Line
APS-2024-029 · 3773.1
Not printed $23.12M 12/29/2028 Not printed 2026-10-06
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - APS Local Plan Submission of the Supplemental Projects for 2026 p. 15
Gore - Hampshire 138 kV Line “At Gore Substation, replace substation conductor and disconnect switches.”
138 kV
2026-09-28* SRRTEP Western
APS local plan submission of the supplemental projects for 2026 RTEP p. 15
Gore - Hampshire 138 kV Line “At Gore Substation, replace substation conductor and disconnect switches.”
2025-08-15 SRRTEP Western
Item 04 - APS Supplemental Projects p. 12
Gore - Hampshire 138 kV Line “At Gore Substation, replace substation conductor and disconnect switches.”

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this