Substation Scout

Ballenger Substation

Named in 2 PJM planning documents for 1 project, from July 7, 2026 to September 8, 2026.

Not stateddescribed as
APSzone
—kV as printed
2mentions

Also printed as: Ballenger

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
New Customer Connection
APS-2026-041
Conceptual $54.99M 11/08/2032 1000 MW 2026-09-08
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
In-service date 12/31/2032 → 11/08/2032 2026-07-07 2026-09-08

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08 TEAC
Item 05 - APS Supplemental Projects p. 8
New Customer Connection No role wording
2026-07-07 TEAC
Item 06 - APS Supplemental Projects p. 3
New Customer Connection No role wording

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.