Substation Scout

Quantum 400

Named in 6 PJM planning documents for 3 projects, from October 8, 2024 to September 8, 2026.

Newdescribed as
APSzone
230 kVkV as printed
7mentions

Described as new: “Build a six breaker, three bay (expandable to four bays), breaker-and-a-half substation (Quantum 400)” — source, page 17

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Doubs – Sage 230 kV New Customer
APS-2023-029 · s3150.2
Not printed $23.2M 12/31/2025 approximately 300 MW 2025-10-08
TEAC
New Customer
APS-2023-029 (s3150.1, s3150.2) · s3150.2
Not printed $23.2M 12/31/2025 approximately 300 MW 2026-09-08*
SRRTEP Western
New Customer Connection
APS-2026-041
Conceptual $54.99M 11/08/2032 1000 MW 2026-09-08
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Cost estimate $23.2M → $20.8M 2025-10-08 Not reported
Cost estimate $20.8M → $8M Not reported Not reported
Cost estimate
prior value printed on the same page
$20.8M → 23.2M 2025-01-07 2025-01-07
Cost estimate $20.8M → 23.2M 2024-10-08 2025-01-07
In-service date 12/31/2025 → 09/01/2025 2025-10-08 Not reported
In-service date 09/01/2025 → 12/31/2027 Not reported Not reported
In-service date 09/01/2025 → 12/31/2025 2024-10-08 2025-01-07
Substations named DOUBS; LIME KILN; QUANTUM 400; SAGE → DOUBS; QUANTUM 400; SAGE Not reported Not reported
In-service date 12/31/2032 → 11/08/2032 2026-07-07 2026-09-08

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08 TEAC
Item 05 - APS Supplemental Projects p. 9
New Customer Connection No role wording
230 kV
2026-09-08* SRRTEP Western
APS local plan submission of the supplemental projects for 2024 RTEP p. 7
Doubs – Sage 230 kV New Customer “Build a six breaker, two bay (expandable to four bays), breaker-and-a-half substation (Quantum 400)”
230 kV
2026-09-08* SRRTEP Western
APS local plan submission of the supplemental projects for 2025 RTEP p. 17
New Customer “Build a six breaker, three bay (expandable to four bays), breaker-and-a-half substation (Quantum 400)”
230 kV
2026-09-08* SRRTEP Western
APS local plan submission of the supplemental projects for 2025 RTEP p. 18
Doubs – Sage 230 kV New Customer “Expand Quantum 400 station to a ten breaker”
230 kV
2025-10-08 TEAC
Informational Only - APS Local Plan Submission of the Supplemental Projects for 2025 p. 17
Doubs – Sage 230 kV New Customer “Build a six breaker, three bay (expandable to four bays), breaker-and-a-half substation (Quantum 400)”
230 kV
2025-01-07 TEAC
Item 05 - APS Supplemental Project p. 7
Doubs – Sage 230 kV New Customer “Build a six breaker, two three bay (expandable to four bays), breaker-and-a-half substation (Quantum 400)”
230 kV
2024-10-08 TEAC
Informational Only - APS Local Plan submission of supplemental project 2024 p. 7
Doubs – Sage 230 kV New Customer “Build a six breaker, two bay (expandable to four bays), breaker-and-a-half substation (Quantum 400)”
230 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this