Kenzie Creek

Named in 5 PJM planning documents for 3 projects, from July 18, 2025 to October 6, 2026.

Existingdescribed as
AEPzone
138/69kV, 138kV, 345 kVkV as printed
6mentions

Also printed as: Kenzie Creek station

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
AEP Transmission Zone: Supplemental S2167 Scope Change
AEP-2018-IM002, AEP-2019-IM035, AEP-2019-IM025, AEP-2019-IM046 · S2167
Conceptual $125.8M 3/13/2026 Not printed 2025-10-08
TEAC
AEP Transmission Zone M-3 Process Project Amazing Sites 100 and 201
AEP-2023-IM023 · s3588.1-.7
Conceptual $184.977M 12/15/2026 1100MW 2025-10-08
TEAC
Dowagiac, MI
AEP-2024-IM011 · s3765.1
Engineering $3.719 M 12/01/2025 5.14 MVA 2026-10-06
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Cost estimate
prior value printed on the same page
$101.3M → $125.8M Not reported Not reported
Cost estimate
prior value printed on the same page
$101.3M → $125.8M 2025-07-18 2025-07-18
Cost estimate
prior value printed on the same page
$101.3M → $125.8M 2025-10-08 2025-10-08
Cost estimate
prior value printed on the same page
$155.69 M → $184.977M 2024-10-08 2024-10-08
Substations named DUMONT; ELDERBERRY; KENZIE CREEK; LARRISON DRIVE; NEW PRAIRIE; OLIVE; SORENSON; THOMSON → DUMONT; ELDERBERRY; LARRISON DRIVE; NEW PRAIRIE; OLIVE; SORENSON 2025-10-08 Not reported

Every mention

DateDocumentProjectWhat the document says about it
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 13
Dowagiac, MI No role wording
138kV
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 13
Dowagiac, MI No role wording
138kV
2026-09-08* SRRTEP Western
AEP local plan submission of the supplemental projects for 2025 RTEP p. 39
AEP Transmission Zone: Supplemental S2167 Scope Change “At Kenzie Creek station, install a 138/69kV XFR”
138/69kV
2025-10-08 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2025 p. 12
AEP Transmission Zone M-3 Process Project Amazing Sites 100 and 201 No role wording
345 kV
2025-10-08 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2025 p. 39
AEP Transmission Zone: Supplemental S2167 Scope Change “install a 138/69kV XFR, 3 138kV breakers, 5 69kV breakers and a 14.4Mvar cap bank”
138/69kV
2025-07-18 SRRTEP Western
Item 04 - AEP Supplemental Projects p. 3
AEP Transmission Zone: Supplemental S2167 Scope Change “At Kenzie Creek station, install a 138/69kV XFR”
138/69kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this