Named in 5 PJM planning documents for 3 projects, from October 8, 2024 to October 6, 2026.

Existingdescribed as
AEPzone
138kV, 69/34.5kVkV as printed
5mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Rothadew Area Improvements
AEP-2022-IM013 · s3136.1-.7
Conceptual $7.89M 7/27/2027 28MW 2024-10-08
TEAC
Hartford - Valley - Corey 138kV Rebuild
AEP-2023-IM011
Conceptual $162.85 M 09/23/2031 Not printed 2026-07-17
SRRTEP Western
Dowagiac, MI
AEP-2024-IM011 · s3765.1
Engineering $3.719 M 12/01/2025 5.14 MVA 2026-10-06
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 13
Dowagiac, MI No role wording
138kV
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 13
Dowagiac, MI No role wording
138kV
2026-09-08* SRRTEP Western
AEP local plan submission of the supplemental projects for 2024 RTEP p. 49
Rothadew Area Improvements “Valley: Install a 69/34.5kV 12.5MVA transformer and reterminate the Rothadew line to the 69kV bus”
69/34.5kV
2026-07-17 SRRTEP Western
Item 04 - AEP Supplemental Projects p. 24
Hartford - Valley - Corey 138kV Rebuild “Station and P&C upgrades to accommodate the main line rebuild.”
2024-10-08 TEAC
Informational Only - AEP Local Plan submission of supplemental projects 2024 p. 49
Rothadew Area Improvements “Install a 69/34.5kV 12.5MVA transformer”
69/34.5kV