Hanging Rock substation interconnection queue

3 active projects totaling 51 MW in the PJM queue, plus 2 with terminal status (shown grayed).

5 PJM queue filings name Hanging Rock as the point of interconnection, all in OH.

Target commercial operation dates as filed run from Jun 2008 to Jun 2027 (5 filings). 1 active filing targets a date after November 27, 2026.

Transmission owner as filed: AEP (1 filing).

3active projects
51active MW
5total filed
Queue IDProjectkVMWResourceStatusTarget COD
X1-027 Hanging Rock 138kV 138 200 Coal Withdrawn Jun 2014
AH1-686 Hanging Rock 765 kV 765 21 Gas Active Jun 2027
T73 Hanging Rock CC2 765 20 Gas In Service Jun 2008
AA1-013 Cornu 765 10 Gas In Service Oct 2015
Y3-096 Hanging Rock 765kV 765 0 Battery Withdrawn Mar 2015

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

PJM planning mentions

A substation with the same name is named in PJM transmission planning materials: Hanging Rock (AEP, 4 mentions).

Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.

Other PJM queue substations in Scioto County, OH

All 7 PJM queue filings in Scioto County, OH.

Other PJM queue substations in Lawrence County, OH

No other substation in Lawrence County, OH is named as a point of interconnection in the PJM queue.

All 8 PJM queue filings in Lawrence County, OH.