White Oak substation interconnection queue
4 active projects totalling 119.5 MW in the PJM queue, plus 1 with terminal status (shown greyed).
4active projects
119.5active MW
5total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| F05_W38 | White Oak 500 kV | 500 | 1,200 | Gas | Withdrawn |
| C01-2010 | White Oak 230 kV | 230 | 100 | Battery | Active |
| P32 | GSA Federal Research Center (FDA) | n/r | 19.5 | Gas | In Service |
| V2-037 | White Oak | n/r | 0 | Gas | In Service |
| W4-010 | White Oak | n/r | 0 | Gas | In Service |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.