Substation Scout

Montgomery, MD interconnection queue

15 active projects totalling 1,683.5 MW in the PJM queue, plus 16 with terminal status (shown greyed).

15active projects
1,683.5active MW
31total filed
Queue IDProjectkVMWResourceStatus
AH1-759 Not reported n/r 600 Battery Withdrawn
U2-084 Dickerson n/r 600 Gas Withdrawn
AG1-483 Fourth Quarter 230 500 Battery EP
C01-1885 Dickerson - Quince Orchard 230 kV 230 500 Battery Active
X3-088 Dickerson 230kV 230 440 Gas Withdrawn
C01-1476 Dickerson - Edwards Ferry 230 kV 230 400 Battery Active
U2-082 Dickerson 230kV 230 400 Gas Withdrawn
B01 Dickerson n/r 398 Gas Withdrawn
G02 Dickerson 230kV 230 234 Gas Withdrawn
C01-2160 Dickerson H 230 kV 230 200 Gas Active
X4-023 Dickerson 230kV 230 155 Not reported Withdrawn
AG2-302 Dickerson 230 kV 230 150 Battery Withdrawn
A07 Dickerson 120 MW n/r 120 Gas Withdrawn
D10 NIH Unit 1 13 25 Other In Service
P32 GSA Federal Research Center (FDA) n/r 19.5 Gas In Service
F07 Dickerson 230 16 Gas In Service
R90 Dickerson-Pleasant View 230kV 230 14 Not reported Withdrawn
J08 GSA Federal Research Center (FDA) n/r 8 Gas In Service
AF2-154 Dickerson HCT1, HCT2, DCT1 230 5 Gas In Service
C01-2264 Sandy 34.5 kV 34.5 5 Battery Active
W3-105 Dickerson CT1 (D-CT1) 230 5 Other Deactivated
M17 Mount Zion 13.8 kV 13.8 4 Gas Withdrawn
S02 Oaks LF 13 4 Gas Deactivated
W4-020 Mt. Zion 13.8kV 13.8 3.8 Solar Withdrawn
D29 Derwood 13kV 13 3 Gas In Service
I10 Bethesda (Sub 6) n/r 2 Gas In Service
S01 Gude LF 13 1 Gas Deactivated
R25 Dickerson - Pleasant View 230kV 230 0 Not reported Withdrawn
V2-037 White Oak n/r 0 Gas In Service
W4-010 White Oak n/r 0 Gas In Service
Y3-074 Ashton 480V n/r 0 Hydro In Service

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.