Dickerson substation interconnection queue
2 active projects totaling 516 MW in the PJM queue, plus 9 with terminal status (shown grayed).
11 PJM queue filings name Dickerson as the point of interconnection, all in MD.
Target commercial operation dates as filed run from Mar 2001 to Feb 2030 (10 filings). 1 active filing targets a date after November 27, 2026.
Transmission owner as filed: PEPCO (1 filing).
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| G50 | Dickerson 230kV | 230 | 910 | Gas | Withdrawn | Dec 2005 |
| U2-084 | Dickerson | n/r | 600 | Gas | Withdrawn | Dec 2012 |
| AG1-483 | Fourth Quarter | 230 | 500 | Battery | EP | Feb 2030 |
| X3-088 | Dickerson 230kV | 230 | 440 | Gas | Withdrawn | Dec 2016 |
| U2-082 | Dickerson 230kV | 230 | 400 | Gas | Withdrawn | Dec 2012 |
| B01 | Dickerson | n/r | 398 | Gas | Withdrawn | n/r |
| G02 | Dickerson 230kV | 230 | 234 | Gas | Withdrawn | May 2006 |
| X4-023 | Dickerson 230kV | 230 | 155 | Not reported | Withdrawn | Jun 2015 |
| AG2-302 | Dickerson 230 kV | 230 | 150 | Battery | Withdrawn | Dec 2023 |
| F07 | Dickerson | 230 | 16 | Gas | In Service | Mar 2001 |
| W3-105 | Dickerson CT1 (D-CT1) | 230 | 5 | Other | Deactivated | Dec 2011 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
PJM planning mentions
A substation with the same name is named in PJM transmission planning materials: Dickerson (PEPCO, 2 mentions).
Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.
Same name on other Substation Scout pages
Other sources that print a substation named “Dickerson” in MD. They are matched by name and state only, so a page listed here may describe a different substation with the same name. Check the location and utility on each. Where a PJM planning record prints no state, the match is by name within the states the utility zone serves, which is weaker.
- Dickerson: Expansion Tracker, PJM planning: APS state not printed
Other PJM queue substations in Frederick County, MD
- Doubs: 2 active, 450 MW of 5 filed
- Stonewall: 2 active, 300 MW of 2 filed
- Carroll-Monocacy: 2 active, 13.3 MW of 2 filed
- Catoctin: none active of 5 filed
- Doubs or: none active of 2 filed
- Metropolitan Court: none active of 2 filed