PJM queue ID C01-2010

White Oak 230 kV (C01-2010) is listed in the PJM interconnection queue as a 100 MW battery project in Henrico County, VA. The filing names White Oak as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of March 1, 2030.

Queue IDC01-2010
Project nameWhite Oak 230 kV
Status (as published)Active
SubstationWhite Oak
Point of interconnectionWhite Oak 230 kV
CountyHenrico
StateVA
Voltage230 kV
Capacity100 MW
Resource (as published)Storage
Resource categoryBattery (normalized for filtering)
Target commercial operation2030-03-01
Source datasetcycle

Same substation and county

White Oak substation: 5 requests in the PJM queue, 4 active totaling 119.5 MW.

Queue IDProjectMWResourceStatus
P32GSA Federal Research Center (FDA)19.5GasIn Service
V2-037White Oak0GasIn Service
W4-010White Oak0GasIn Service
F05_W38White Oak 500 kV1,200GasWithdrawn

Henrico, VA: 17 requests in the PJM queue, 11 active totaling 227.7 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

DeveloperViridity Energy Solutions Inc
Transmission ownerDominion
Project typeGeneration Interconnection
CycleC01
StagePhase 1
MW energy100.0
MW capacity100.0
MFO100.0
Submitted date4/27/2026
Last updated6/18/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first