Otter Creek Solar
PJM queue ID AF2-142
Otter Creek Solar (AF2-142) is listed in the PJM interconnection queue as a 90 MW solar project in Lasalle County, IL. The filing names Nevada as its point of interconnection. PJM lists its status as “EP”, with a target commercial operation date of May 28, 2029.
| Queue ID | AF2-142 |
|---|---|
| Project name | Otter Creek Solar |
| Status (as published) | EP |
| Substation | Nevada |
| Point of interconnection | Nevada 345 kV |
| County | Lasalle |
| State | IL |
| Voltage | 345 kV |
| Capacity | 90 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2029-05-28 |
| Source dataset | cycle |
Same substation and county
Nevada substation: 2 requests in the PJM queue, 1 active totaling 90 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| AD1-116 | Nevada 345 kV | 7.6 | Solar | Withdrawn |
Lasalle, IL: 27 requests in the PJM queue, 11 active totaling 530.5 MW.
A substation with the same name is named in PJM transmission planning materials: Nevada (COMED, 4 mentions).
Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Developer | Aurora Solar LLC |
|---|---|
| Transmission owner | ComEd |
| Project type | Generation Interconnection |
| Cycle | TC1 |
| Stage | FINAL AGREEMENT |
| MW energy | 150.0 |
| MW capacity | 90.0 |
| MFO | 150.0 |
| Submitted date | 3/12/2020 |
| Last updated | 3/9/2026 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.